Client name: Henry Yue Trading Ltd
Sites: Two sites in Hobsonville, Auckland
Project overview: New dwellings (one per site) with a swimming pool and earthworks on both sites
Goal: Resource consent
Process: The resource consent process for each site was smooth and achieved quickly without any Section 92 requests due to the work of our planning team in providing a comprehensive application.
Outcome: Resource consents obtained.
The value that Thomas Consultants team added: Provided a tailored service for the project so that the client properly understood the process and was updated every step of the way. Avoided s92 so the process was quicker than the standard timeframe for resource consent approval.
Partners we worked with on the project: Y-Day Design Ltd (architects)
Services provided: Planning
Completion date: Resource consents granted on 10th and 12th May 2022